MEMORANDUM

QUESTION 1: SAFETY AND MATERIALS (GENERIC)
1.1
1.1.1 2 (1)
1.1.2 228 mm (1)
1.1.3 900 mm (1)
1.1.4 150 mm (1)
1.1.5 Non-slippery layer (1)
1.2 Similar answer:

  • Prevents horizontal movement between the platform and structure (1)

1.3 Identify THREE of the following requirements that are applicable to the supplier of hazardous chemical substances:
1.3.1 First-aid measures must be indicated
1.3.4 Fire-fighting measures must be indicated
1.3.6 Storage instructions must be indicated (3 x 1) (3)
1.4 Minimum = 30⁰ (1) and maximum = 50⁰ (1) (2)
1.5 Similar answer:

  • Aluminium conducts electricity (1) and workers who use a ladder could be shocked (1) (2)

1.6 Describe the difference between the surface finish of a water-based paint and an oil-based paint:

  • Water-based – provide an elastic, flexible finish (1) Oil-based – provide a hard, durable finish (1) (2)

1.7 Any THREE advantages of the curing of concrete:

  • Increases strength
  • Decreases permeability
  • Improves durability
  • Reduces cracks
  • Makes concrete more watertight
  • Provides volume stability
  • Concrete can carry more weight (3 x 1) (3)

1.8 Briefly describe the powder coating process:

  • Plastic finish in powder form (1) is applied through a compressed air spray-gun (1) (2)

[20]

QUESTION 2: GRAPHICS, JOINING AND EQUIPMENT (GENERIC)
2.1 Answer the following questions with regard to the site plan on ANSWER SHEET A:
2.1.1 See ANSWER SHEET A (10)
2.1.2 See ANSWER SHEET A (6)
2.2
2.2.1 Undisturbed earth 2.2.1 ADYT (2)
2.2.2 Plaster 2.2. uygyda(2)
2.2.3 Ramp with a slope of 1 : 5 1:5 2.2.3 afdtya(2)
2.2.4 Electrical meter W 2.2.4 auyygduya(2)
2.2.5 Sink unit – double 2.2.5 uafgdyad(2)
2.3
2.3.1 2.3.1 ayfdtyadUnfinished wood (1)
2.3.2 2.3.2 auygdaTwo-way switch (1)
2.4 When driven into place (1) it cannot be turned (1) (2)
2.5 Prevents backing off OR it acts as a lock nut (1)
2.6 18 mm (1)
2.7
2.7.1 1,35 m (1)
2.7.2 1,412 – 1,285 = 0,127 x 100 = 12,7m (0,1m leeway allowed) (3)
2.7.3 Minimum = 30 m (1) and maximum = 200 m (1) (2)
2.8 It can affect the measuring function of the tool. (1)
2.9 Batteries must be removed. (1)
[40]
TOTAL SECTION A: 60

QUESTION 3: CASEMENTS, CUPBOARDS, WALL-PANELLING AND QUANTITIES (SPECIFIC)
3.1 3.1.1 16 mm (1)
3.1.2 Stuck mould (1)
3.1.3 Rebate (1)
3.2
3.2.1 Drip groove (1)
3.2.2 Transom

  • Bottom rail of fanlight 60 mm x 44 mm Putty
  • Ovol moulding
  • Windowpane/glass (3 x 1) (3)

3.2.3 Enhances the appearance and can open separately to allow ventilation (1)
3.3 ANSWER SHEET B (5)
3.4
3.4.1

  • Top shelf/storage space
  • Hanging space
  • Shelving
  • Drawer unit (4)

3.4.2

  • Melamine is waterproof
  • Easy to clean
  • Durable
  • Smooth finish
  • Improves appearance (Any 1) (1)

3.4.3

  • E = Front rail G = Side of cabinet
  • F = Handrail H = Kick plate (4)

3.5 Fanlight (1)
3.6
3.6.1

  • A = Cornice
  • B = Horizontal rough grounds
  • C = Quadrant mould (3)

3.6.2

  • Provide storage space
  • Improves/enhances the aesthetic appeal of the room
  • Looks expensive (2)

3.7 A casement window can be defined as a window assembly that has at least one casement or vertically hinged sash (frame that holds the glass) (2)
[30]

QUESTION 4: ROOFS, CEILINGS, TOOLS AND EQUIPMENT, AND MATERIALS (SPECIFIC)
4.1
4.1.1 A = Router B = Radial arm saw (2)
4.1.2

  • Lubricate and adjust according to the manufacturer’s instructions
  • Clean the saw after use
  • Repair or replace damaged electrical cords
  • Use machinery only for the intended purpose
  • Keep ventilation holes open and clean (2)

4.1.3

  • Always wear safety goggles
  • Use both hands to operate the machine
  • Stand firmly and comfortably
  • Wear a dusk mask when using the router
  • The workpiece must be gripped firmly before starting the moulding (2)

4.2

  • Gypsum ceiling board
  • Cover strips
  • Trapdoor panel
  • Tie beam (2)

4.3

  • Sand the wood with different grades of sandpaper
  • Sand until it is smooth and free from scratches
  • Remove all dust (3)

4.4 Hurricane clips:

  • Securing purlins to rafter (roof truss)
  • Securing trusses to wall plates
  • Ideally used at eaves overhangs
  • Where trusses cross each other or where truss members cross each other or meet at 90°
  • To fix opposite faces of roof members
    Storm clips: Securing roof tiles to the battens (2)

4.5

  • Strength
  • Density (2)

4.6

  • King post positioned in the middle of the roof truss
  • Brandering is nailed to the tie beam and to existing brandering
  • Roof sheeting to cover the roof (3)

4.7

  • Always wear safety goggles
  • Wear a dusk mask when using the belt sander
  • Inspect the power cord regularly for damage
  • Avoid carrying the machine by the cord (2)

4.8
4.8.1

  • A. Tie beam
  • B. Brandering
  • C. Brandering
  • D. Trapdoor
  • E. Ceiling board (5)

4.8.2 Cover strips keep the panels in place (2)
4.8.3
4.8.3 ighduyad
Sectional view showing a metal T-strip (3)
4.9
4.9.1

  • A. Hipped end
  • B. Purlin
  • C. Ridge
  • D. Valley rafter
  • E. Overhang
  • F. Gable end (6)

4.9.2 75 mm x 50 mm (2)
4.10

  • Must be able to withstand natural elements like rain, wind and corrosion
  • Must look expensive and must be able to improve the appearance of the building
  • Must be able to withstand fire
  • To insulate against heat and cold    (2)

[40]

QUESTION 5: CENTRING, FORMWORK,SHORING AND GRAPHICS AS MEANS OF COMMUNICATION (SPECIFIC)
5.1

  • Plastic
  • Metal sheeting
  • Hardboard
  • Fibreglass (1)

5.2 ANSWER SHEET C (6)
5.3
5.3.1 Double flying shore: used to provide temporary support to two parallel walls that are located between 9 metres and 15 metres apart where one or both walls show signs of failure (1)
5.3.2 Dead shore:

  • Support structures
  • Carry the dead weight of the structure above them, for example walls and floors
  • New openings for existing walls and doors underpinning, is needed during restoration of the wall (1)

5.4
5.4.1 Steel dogs: nails used to secure the joint between prop and needle (1)
5.4.1 Sole plate: made of timber to spread the weight transferred by the props over a wider area (1)
5.4.3 Props or struts: placed vertically on top of each other on the different floors to strengthen or brace the floors and ceilings (1)
5.5
5.5.1

  • A – Concrete/floor slab
  • B – Brace/strut
  • C – Prop
  • D – Sole plate (4)

5.5.2

  • To support the formwork
  • Keep the different formwork components sturdy and fixed
  • Facilitate the raising or lowering of the formwork to the required height
  • For levelling the formwork
  • Ease the striking of formwork after the concrete has cured (4)

5.6

5.6 suigyfs

ASSESSMENT CRITERIA   MARK 
Beam  1
Ribs  2
Two labels  2
Correctness of drawing  1
TOTAL:   6

(6)
5.7
5.7.1

  • To lower
  • To raise the centre (2)

5.7.2

  • Table saw
  • Bandsaw
  • Jigsaw
  • Portable circular saw
  • Circular saw (Any 2) (2)

[30]

QUESTION 6: SUSPENDED FLOORS, STAIRCASES, IRONMONGERY, DOORS AND JOINING (SPECIFIC)
6.1

  • A. Place to rest
  • B. For safety reasons in case of an accident
  • C. Change of direction (2)

6.2 

6.2 aihgda

(5)
6.3

  • On a cupboard door
  • On a drawer (2)

6.4 Night latch (1)
6.5
6.5 suygtys
Correctness

ASSESSMENT CRITERIA   MARK 
 Muntin  1
 Raised panels  2
 Space for expansion and shrinkage  1
 Hatching  1
 Correctness of drawing  1
 TOTAL  6

(6)
6.6 The opening allows for shrinkage and expansion of wood (1)
6.7
6.7.1 A: Brace B: Tongue and groove panels C: Stile (3)
6.7.2 To prevent sagging (1)
6.7.3 Gives a neater appearance at the outside of the frame members (1)
6.8

6.8 suygys

ASSESSMENT CRITERIA   MARK 
 Walls  2
 Frame profile of door  1
 Jamb lining profile  1
 Title  1
 Architraves  1
 TOTAL:  6

6.9
6.9.1

  • A = 220mm wall
  • E = Floor joist
  • B = 12 mm plaster F = Wall plate/bearers
  • C = Skirting G = Damp-proof course (DPC)
  • D = Floorboard H = Foundation (8)

6.9.2 To cover the gaps between the flooring and the wall (1)
6.9.3

  • Span of the floor
  • The centre-to-spacing between the floor joist; and
  • The grade of timber of the floor (3)

[40]
TOTAL: 200

ANSWER SHEET A
2.1 Answer the following questions with regard to the site plan on ANSWER SHEET A:
2.1.1 Any TEN particulars that are not shown according to the checklist:

  • Plot no. 31 is not shown
  • Plot depth measurement is not shown
  • Street name is not shown
  • Branch sewage at S is not shown
  • Connecting manhole (1,5 m inside plot boundary) is not shown
  • Measurements of southern building boundary are not shown
  • Structure measurements are not shown
  • RE (rodding eye) symbol is not shown
  • IE symbols are not shown
  • VP and symbol are not shown at WC
  • Entrance to plot is not shown
  • No datum level is shown (10)

2.1.2 Identify SIX particulars that are shown incorrectly on the site plan:

  • Construction is over the building boundary on the west side
  • North arrow must be right-hand side, at the bottom of the page
  • Scale is shown incorrectly
  • Corner of branch sewage at WB incorrect
  • RE and symbol missing at the change of direction in sewage line
  • House depth measurements are not shown (6)

ANSWER SHEET B
QUESTION 3.3

3.3 uyguys 

ASSESSMENT CRITERIA   MARK 
 Wall  1
 Capping  1
 Rough ground  1
 Tongue and groove board  1
 Correctness of drawing  1
 TOTAL:  6

ANSWER SHEET C
QUESTION 5.2

5.2 aiyhgda

ASSESSMENT CRITERIA   MARK 
 Stile   1
 Top rail   1
 Mortise  1
 Haunch  2
 Application of scale  1
 TOTAL:  6
Last modified on Wednesday, 23 February 2022 11:38