QUESTION 1: SAFETY, OHSA AND MATERIAL (GENERIC)
1.1 3 m (1)
1.2 (1) By means of a chute or (2) conveyor belt (2)
1.3 Similar answer:
1.4
1.4.1
1.4.2
1.5
1.6 (1) Not further than 2/3 (2) of the extension length (2)
1.7 (1) The coating of a metal by means of electrolysis (2) with a thin layer of another metal. (2)
1.8 Any THREE advantages of electroplating of metals:
1.9 Any TWO advantages of galvanising metals:
QUESTION 2: GRAPHICS, JOINING AND EQUIPMENT (GENERIC)
2.1
2.1.1 False (1)
2.1.2 True (1)
2.1.3 True (1)
2.1.4 True (1)
2.1.5 False (1)
2.2 FIGURE 2.2 on ANSWER SHEET A:
2.2.1 Outside door at 2.2.A (2)
2.2.2 Window at 2.2.B (2)
2.2.3 Water closet at 2.2.C (2)
2.2.4 Washbasin at 2.2.D (2)
2.2.5 Single sink unit at 2.2.E (2)
2.2.6 One-way switch single pole at 2.2.F (2)
2.2.7 Fluorescent light at 2.2.G (2)
2.2.8 Socket outlet at 2.2.H (2)
2.2.9 Grease trap at 2.2.I (2)
2.2.10 Wall-mounted light at 2.2.J (2)
2.3
2.3.1 Trim hexagon
2.3.2 Hex flange
2.3.3 Square shoulder screws (3)
2.4
2.4.1 Dumpy level (1)
2.4.2 Any ONE use of this instrument:
2.4.3
2.4.4 (1) To obtain a level / horizontal (2) sight line / reading (2)
2.5 (1) If the moisture inside the level freezes and later reaches normal operating temperature, the moisture can condense (2) inside the tool, where it may damage the circuit board (2)
2.6
QUESTION 3: ROOFS, STAIRCASES AND JOINING (SPECIFIC)
3.1
3.1.1 Flat roof (1)
3.1.2 Mono-pitched roof (1)
3.1.3 1 400 mm / 1,4 m (1)
3.1.4 38 x 38 mm (1)
3.2 Any THREE requirements that roof trusses should meet:
3.3 Any THREE advantages with the use of roof underlays:
3.4
3.4.1 South African roof / Howe roof (1)
3.4.2 A – Rafter (1) B – Queen post (1) C – King post (1) D – Strut (1)
3.4.3 Span width more than 5 m (1)
3.4.4 114 (1) x 38 mm (1) (2)
3.5 Any TWO types of materials that staircases can be made from:
3.6 (4)
3.7 2 100 mm / 2,1 m (1)
3.8 100 mm (1)
3.9
3.9.1 Anchor / Galvanised steel straps / Hoop iron / Wires (1)
3.9.2 Bolted / Nailed / Galv. steel straps / Hoop iron / Wires (1)
3.9.3 Bolted / Welded / Glued (1)
3.9.4 Cast-in anchors / Bolted (1) [30]
QUESTION 4: MATERIAL, EXCAVATIONS, EQUIPMENT AND TOOLS (SPECIFIC)
4.1
4.1.1 F (tested on site) (1)
4.1.2 G (high volume of concrete) (1)
4.1.3 E (ferrous metals) (1)
4.1.4 C (tested in a laboratory) (1)
4.1.5 A (small volume of concrete) (1)
4.1.6 B (non-ferrous metals) (1)
4.2 Any FOUR types of apparatus for the slump test:
4.3 Any TWO – Discuss the purposes of the cube test:
4.4 Draw a neat sketch of a normal failure of a cube test:
(3)
4.5 Any TWO – Discuss the purposes of cladding to external surfaces of buildings:
4.6 Any TWO methods of fixing cladding:
4.7 Any THREE safety factors and regulations that a site manager must have in place, before excavation commences:
4.8
4.8.1 Fencing / Warning signs / Warning lights / Covering (1)
4.8.2 All workers must wear protective clothing (1)
4.8.3 With a ladder / scaffolding (1)
4.8.4 Inspections must be done daily (1)
4.9
4.9.1 True (1)
4.9.2 True (1)
4.9.3 False (1)
4.9.4 False (1)
4.10
4.10.1 Firm ground / Hard ground (1)
4.10.2
4.11
4.11.1 Plate compactor (1)
4.11.2 Any THREE ways to care and maintain the plate compactor:
QUESTION 5: BRICKWORK, GRAPHICS, PLASTER AND SCREED (SPECIFIC)
5.1
5.1.1 Cavity wall (1)
5.1.2 270 mm (1)
5.1.3 Any THREE purposes of the gap in a cavity wall:
5.2
5.2.1 Bedding sand (1)
5.2.2 Weep hole (1)
5.2.3 Pavements (1)
5.2.4 Air bricks (1)
5.2.5 Subgrade (1)
5.3
5.3.1 Butterfly pattern (1)
5.4 Any FOUR advantages of dry-laid paving:
5.5 Any TWO reasons for construction failure of paving:
5.6 Draw a neat partial sketch of the herringbone paving pattern:
(3)
5.7 Any THREE advantages of beam filling:
5.8
5.8.1 True (1)
5.8.2 False (1)
5.8.3 True (1)
5.9
5.9.1 Semi-circular gauged arch (1)
5.9.2
5.10 Sand (1) and cement (1) (2)
5.11 Any ONE purpose of builder’s lime in a plaster mixture:
5.12 Any TWO uses / purposes of interior plasterwork:
5.13 Any ONE purpose of a screed layer:
5.14
5.14.1(2)
5.14.2 (2)
[40]
QUESTION 6: FORMWORK, REINFORCEMENT, FOUNDATIONS, CONCRETE FLOORS AND QUANTITIES (SPECIFIC)
6.1 Any ONE material that can be used to line the formwork, to obtain a smoother finish:
6.2
6.2.1
6.3
6.3.1 Soft / mild steel (1)
6.3.2 200 mm (1)
6.3.3 10 mm (1)
6.4
6.4.1 Compressive forces (Anchor bars) (1)
6.4.2 Shear forces (Stirrups) (1)
6.5 Any ONE method of joining steel bars with wire:
6.6 Any TWO purposes of the cover depth at the reinforcing of concrete work:
6.7 Any TWO types of pile foundations:
6.8 Any THREE reasons for using pile foundations:
6.9
6.9.1 A Hollow-core blocks / Concrete floor block (1) B Rib / Reinforced ribs / Pre-stressed ribs (1)
6.9.2 Any ONE disadvantage of the rib-and-block floor construction:
6.10 Foundation strip - outside room is 5 500 x 3 250 (outside measurements). The foundation is 700 mm wide and 200 mm thick.
6.10.1 Calculate the centre-line of the foundation:
6.10.2 Calculate the volume of concrete required:
TOTAL: 200
ANSWER SHEET A | CIVIL TECHNOLOGY GENERIC | NAME: |
2.2 Use the information on sheet A and complete the floorplan to scale 1 : 100.
Outside door at 2.2.A | 2 | |
Window at 2.2.B | 2 | |
Water closet at 2.2.C | 2 | |
Wash basin at 2.2.D | 2 | |
Single sink unit at 2.2.E | 2 | |
One-way switch single pole at 2.2.F | 2 | |
Fluorescent light at 2.2.G | 2 | |
Socket outlet at 2.2.H | 2 | |
Grease trap at 2.2.I | 2 | |
Wall-mounted light at 2.2.J TOTAL: 20 | 2 | |