QUESTION 1: SAFETY AND MATERIALS (GENERIC) 1.1 1.1.1 2 (1) 1.1.2 228 mm (1) 1.1.3 900 mm (1) 1.1.4 150 mm (1) 1.1.5 Non-slippery layer (1) 1.2 Similar answer:
Prevents horizontal movement between the platform and structure(1)
1.3 Identify THREE of the following requirements that are applicable to the supplier of hazardous chemical substances: 1.3.1 First-aid measures must be shown 1.3.4 Fire-fighting measures must be shown 1.3.6 Storage instructions must be shown (3 x 1) (3) 1.4 Minimum = 30⁰ (1) and maximum = 50⁰ (1) (2) 1.5 Similar answer:
Aluminium conducts electricity (1) and workers who use a ladder could be shocked (1) (2)
1.6 Describe the difference between the surface finish of a water-based paint and an oil-based paint:
Water-based – provides an elastic, flexible finish (1) Oil-based – provides a hard, durable finish (1) (2)
1.7 Any THREE advantages of the curing of concrete:
Increases strength
Decreases permeability
Improves durability
Reduces cracks
Makes concrete more watertight
Provides volume stability
Concrete can carry more weight (3 x 1) (3)
1.8 Briefly describe the powder-coating process:
Plastic finish in powder form (1) is applied by means of a compressed air spray- gun (1) (2)
[20]
QUESTION 2: GRAPHICS, JOINING AND EQUIPMENT (GENERIC) 2.1 Answer the following questions with regard to the site plan on ANSWER SHEET A. 2.1.1 See ANSWER SHEET A (10) 2.1.2 See ANSWER SHEET A (6) 2.2 2.2.1 (2)
2.2.2 (2)
2.2.3 (2)
2.2.4 (2)
2.2.5 (2)
2.3 2.3.1 Unfinished wood (1) 2.3.2 Two-way switch (1) 2.4 When driven into place (1) it cannot be turned (1) (2) 2.5 Prevents backing off OR it acts as a lock nut (1) (1) 2.6 18 mm (1) 2.7 2.7.1 1,35 m (1) 2.7.2 1,412 – 1,285 = 0,127 x 100 = 12,7 m (0,1 m leeway allowed) (3) 2.7.3 Minimum = 30 m (1) and maximum = 200 m (1) (2) 2.8 It can affect the measuring function of the tool. (1) 2.9 Batteries must be removed. (1) [40] TOTAL SECTION A: 60
QUESTION 3: ROOFS, STAIRS AND JOINING (SPECIFIC) 3.1 Any FOUR types of roofs or roof trusses:
South African roof truss
Single Howe truss
Lean-to-roof
Couple roof
Closed couple roof
Collar-tie roof
King post roof truss
W-truss or Fink truss
Fan truss
Scissors truss
Mono-pitched roof (4 x 1) (4)
3.2 Any FOUR advantages of the use of roof underlays:
Acts as a secondary roof
A weather shield during construction
Waterproof and weatherproof
Condensation barrier
Dustproof
Protects the building/structure
Protects thermal insulation material
Protects ceiling boards
Superior wind uplifting strength prevents lifting of tiles
Vapour resistant
High tensile resistance
Cost effective
High heat resistance (4 x 1) (4)
3.3 3.3.1
A – Purlin / Batten (1)
B – Rafter (1)
C – Ridge tile / ridge plate (1)
D – Nail plate (1)
E – King post (1)
3.3.2 38 mm (1) x 114 mm (1) (2) 3.3.3 Holds/fixes the different timber pieces together (1) 3.4 3.4.1 Concrete tiles, clay or slate /heavy roofs (1) 3.4.2 Thatched roofs (1) 3.4.3 Iron sheeting/steel roof sheets/corrugated/IBR (1) 3.5 3.5.1 True (1) 3.5.2 False (1) 3.5.3 True (1) 3.5.4 True 3.6 3.6.1 Joining roof truss to brickwork (1) 3.6.2
A – Galvanized steel strap / hoop-iron strap (1)
B – Wall plate (1)
3.6.3 600 mm (1) 3.6.4 Nailed / Bolted (1) 3.7 Any TWO types of cast-in anchors:
Hex-head bolt with washer
L-bolt
J-bolt
Welded headed stud (2 x 1) (2)
[30]
QUESTION 4: MATERIAL, EQUIPMENT AND TOOLS, EXCAVATIONS (SPECIFIC) 4.1 4.1.1 D hard, but brittle and breaks easily (1) 4.1.2 H pumps high volumes of concrete (1) 4.1.3 G alloy of copper and zinc (1) 4.1.4 C pumps smaller volumes of concrete (1) 4.1.5 A highly toxic (1) 4.1.6 E packaging material (1) 4.2 4.2.1 Slump test (1) 4.2.2 100 mm (1) 4.2.3 600 mm (1) 4.2.4 Any TWO reasons for the purposes of the slump test:
To test the density of concrete (percentage water)
To determine the workability and consistency of batches
To determine the slump of the mixture (2 x 1) (2)
4.3 Any TWO ways of curing concrete:
Water by means of hosepipe or sprinkling
Cover with water-retaining substances such as damp sand, sacking, straw, hessian and canvas
Plastic membrane and plastic sheets
Commercial sealant
Pool forming
Similar answer (2 x 1) (2)
4.4 Ferrous (1) and non-ferrous metals (1) (2) 4.5 Any THREE types of cladding for buildings:
Tile cladding
Brick slip cladding
Stone cladding
Timber cladding
Metal sheet cladding (3 x 1) (3)
4.6 4.6.1 Tamping rammer(1) 4.6.2 Any THREE ways of maintaining the tamping rammer:
Lubricate and adjust according to manufacturer’s instructions
4.6.3 To keep control of the powerful machine (1) 4.7 Any FOUR causes for the collapse of an excavation:
Heavy rains
Poor soil strata, structure or composition
Sides not dug at the correct angle
Improper use of formwork or shoring to support walls
Vibration by machinery or heavy vechiles nearby
Water seeping into the excavated area
Contact with underground service
Access to and exit from the excavation
Soil slides due to cracks or loose soil (4 x 1) (4)
4.8 Any THREE ways of making excavations safe during the night:
Fencing
Warning signs
Warning lights (red or orange)
Covering (3 x 1) (3)
4.9 4.9.1 With a ladder/scaffolding (1) 4.9.2 Avoid trench sides from collapsing (one metre away) (1) 4.9.3 Test for low oxygen, hazardous fumes and toxic gases (1) 4.10 4.10.1 False (1) 4.10.2 False (1) 4.10.3 False (1) 4.11 4.11.1 Firm soil/Hard soil/Stable soil (1) 4.11.2
A – Strut (1)
B – Walling board (1)
C – Wedge (1)
[40]
QUESTION 5: BRICKWORK AND GRAPHICS (SPECIFIC) 5.1 5.1.1 One brick wall / Outside wall (1) 5.1.2 220 mm (1) 5.1.3 Stretcher bond (1) 5.2 Any THREE advantages of cavity walls:
Prevent rainwater from penetrating the interior wall surface
Provide good thermal and sound insulation
Cheaper materials can be used for internal walls
Reduces / prevent expensive exterior finishes (3 x 1) (3)
5.3 See ANSWER SHEET B. (5) 5.4 5.4.1 50 mm (1) 5.4.2 8 m (1) 5.4.3 To remove wasted mortar (1) 5.4.4 Wall ties (1) 5.4.5 Allows water that penetrates the outside wall to drain (1) 5.5 Double triangular pattern (1) 5.6 5.6.1
A – Beam filling (1)
B – Fascia board (1)
C – Tie beam (1)
D – Plaster (1)
5.6.2 Open eave construction (1) 5.7 5.7.1 F (prepared layer beneath paving and bedding sand) (1) 5.7.2 C (best edge restraint for paving) (1) 5.7.3 A (natural soil on which the paving will be laid) (1) 5.7.4 D (final layer upon which paving is laid) (1) 5.8 Any TWO advantages of mortar-set paving:
Little maintenance is required
Low life-cycle cost
Resistant to point loads
Resistant to fatigue and reflecting traffic patterns
Resistant to edge movement
User-friendly installation material is used
No weeds will be able to grow in between the joints
No off-gassing installation products used
Insects will not be able to ruin the appearance of the paved structure (2 x 1) (2)
5.9 Any TWO reasons for construction failure of paving:
Concrete haunch too thin to support itself and cracks or crumbles under pressure
Too little weight to retain the structure and keep paving in place
Bond between haunch and edge units is weak and will easily crumble
Sub base is not contained and will be washed out by groundwater (2 x 1) (2)
5.10 Draw a neat sketch with EIGHT (8) bricks of the basket-weave paving:
Bricks drawn in good proportion = (5) 5.11 5.11.1 Segmental gauged arch (1) 5.11.2
A – Key brick (1)
B – Skewback (1)
C – Intrados (1)
D – Extrados (1)
[40]
QUESTION 6: FORMWORK, REINFORCEMENT, FOUNDATIONS, CONCRETE FLOORS AND QUANTITIES (SPECIFIC) 6.1 Concrete is mixed / poured on site (1) 6.2 Any THREE properties of good formwork:
Made accurately according to the dimensions indicated
Sturdy enough to bear the mass of wet concrete without collapsing
Able to bear the mass of workers and equipment
Must be strong enough to provide sufficient support, without too much deflection, until the concrete has set
Formwork should be easy to repair on site
Secured with wire nails, where some should protrude for easy extracting
Secured with bolts from 13 mm to 19 mm in diameter
Should be sealed properly so that the concrete does not leak and form honeycombs or fins
Should be free of dirt (sawdust or releasing agents)
Quick and simple to erect, mechanically or by hand
Ensure the correct cover depth for reinforcing, to prevent structural failure
Fit plywood onto laggings if a smooth finish is required
Remove when the concrete has cured and is able to support load on its own
Should be easy to remove withou damaging the formwork or concrete
Close-fitting along seams and joints
Made from recyclable components (3 x 1) (3)
6.3 6.3.1
A – Soffit / Shutter board (1)
B – Strut / Prop (1)
C – Bearer / Head tree (1)
D – Brace / Strut (1)
E – Folding wedges (1)
6.3.2 Beam (1) 6.4 6.4.1 High-tensile steel (1) 6.4.2 250 mm (1) 6.4.3 16 mm (1) 6.5 6.5.1 Tensile stress / force (1) 6.5.2 Shear stress / force (1) 6.6 Any THREE properties (requirements) for reinforced steel bars:
Free of salt spray, mud, splinters and any oiliness
Completely covered in concrete to protect it against rust and fire hazards
Resistant to tensile stress
Easy to bend into shape
Able to bind firmly with concrete
Of limited expansion prevent tension when temperature fluctuates
Readily available and affordable
Must be rustproof, otherwise it will impair binding (3 x 1) (3)
6.7 Any TWO types of pile foundations:
Precast concrete piles / prefabricated piles
Steel tube caisson piles
In-situ (driven) foundation piles
Short-bored (auger) piles (2 x 1) (2)
6.8 Any TWO reasons for using pile foundations:
Ground conditions not stable / solid enough
Distribute the load to more stable ground (underground / water supports)
Provides stability when raft / floating foundation is used
When structures are subjected to horizontal forces, resist pile foundations bending stress while still lending vertical support
Soils prone to swelling and shrinking (clay soil)
Superstructure is exposed to uplifting forces (offshore platforms)
Where soil erosion is possible (bridges) (2 x 1) (2)
6.9 Foundation strips for a store-room is 5 650 x 3 375 (inside measurements) The foundation is 750 mm wide and 250 mm deep (thick) 6.9.1 Calculate the centre line of the foundation: (5)
Volume = length x width x depth = 21,05 m x 0,75 m x 0,25 m = 3,947 m³ (3)
[30] TOTAL: 200
ANSWER SHEET A 2.1 Answer the following questions in regard to the site plan on ANSWER SHEET A: 2.1.1 Any TEN particulars that are not shown according to the checklist:
Plot no. 31 is not shown
Plots depth measurement is not shown
Street name is not shown
Branch sewage at S is not shown
Connecting manhole (1,5m inside plot boundary) is not shown
Measurements of southern building boundary is not shown
Structure measurements are not shown
RE (rodding eye) symbol is not shown
IE symbols are not shown
VP and symbol are not shown at WC
Entrance to plot is not shown
No datum level is shown (10)
2.1.2 Identify SIX particulars that are shown incorrectly on the site plan:
Construction is over the building boundary on the west side
North arrow must be on the right-hand side, at the bottom of the page
Scale is wrongly shown
Corner of branch sewage at WB is wrong
RE and symbol missing at the change of direction in sewage line
House depth measurements are not shown (6)
ANSWER SHEET B 5.3 Draw in the damp-proof course (DPC). (5)
Last modified on Wednesday, 23 February 2022 11:59