CIVIL TECHNOLOGY PAPER
GRADE 12 
NSC EXAM PAPERS AND MEMOS
NOVEMBER 2016

REQUIREMENTS: 

  1. Drawing instruments
  2. A non-programmable calculator
  3. ANSWER BOOK 

INSTRUCTIONS AND INFORMATION 

  1. This question paper consists of SIX questions. 
  2. Answer ALL the questions. 
  3. Answer each question as a whole. Do NOT separate subsections of  questions.
  4. Start the answer to EACH question on a NEW page.
  5. Do NOT write in the margins of the ANSWER BOOK. 
  6. You may use sketches to illustrate your answers. 
  7. Write ALL calculations and answers in the ANSWER BOOK or on the  attached ANSWER SHEETS.
  8. Use the mark allocation as a guide to the length of your answers.
  9. Make drawings and sketches in pencil, fully dimensioned and neatly finished  off with descriptive titles and notes to conform to the SANS/SABS Code of  Practice for Building Drawings.
  10. For the purpose of this question paper, the size of a brick should be taken as  220 mm x 110 mm x 75 mm. 
  11. Use your own discretion where dimensions and/or details have been omitted.
  12. Answer QUESTIONS 1.3, 1.8.2, 3.11, 4.3, 5.2, 5.3, 6.1 and 6.2 on the attached ANSWER SHEETS using drawing instruments where necessary.
  13. Write your CENTRE NUMBER and EXAMINATION NUMBER on every  ANSWER SHEET and hand them in with your ANSWER BOOK, whether you  have used them or not.
  14. Due to electronic transfer, drawings in the question paper are NOT to scale.

QUESTIONS

QUESTION 1: CONSTRUCTION, SAFETY AND MATERIAL  
1.1 FIGURE 1.1 below shows a person working on a building site. 
68 a person working on a building site.
[Source: miryaglobalmedia] 
FIGURE 1.1 (above)
1.1.1 Study FIGURE 1.1 and describe TWO aspects that the person should have considered to prevent this accident. (2)                                                                     

1.1.2 Name TWO personal safety items that this person is wearing. (2) 
1.1.3 Motivate why you think it is appropriate to wear ear protection  when working with this power tool. (2) 
1.1.4 Recommend ONE other important safety item that the person  should have worn. (1) 

1.2 Freshly cast concrete should be cured. 

1.2.1 Describe what may be used to cure freshly cast concrete. (1)
1.2.2 State the duration of curing. (1)

1.3 FIGURE 1.3 below shows an incomplete sectional view of a wall and roof  construction.  
Use ANSWER SHEET 1.3 and complete the sketch by drawing the following: 

  • Beam filling 
  • The wall plate 
  • Corrugated iron sheeting
  • Label any TWO parts of the drawing. 
    1.3 ct(6) 

1.4 Give TWO reasons why a roof covered with concrete tiles is more expensive  than a roof covered with corrugated iron sheets. (2) 
1.5 Recommend ONE material that you would use to finish a plastered wall in  a bathroom. (1) 
1.6 Give a reason for your answer to QUESTION 1.5. (1)
1.7 FIGURE 1.7 below shows a steel profile. 
1.7ct

1.7.1 Identify the steel profile. (1) 
1.7.2 Describe ONE effect that the weather will have on exposed, untreated steel profiles. (1) 
1.7.3 How would you prevent the effect that you have described in  QUESTION 1.7.2? (1) 
1.7.4 State ONE use of the steel profile. (1) 

1.8 FIGURE 1.8 below shows the front elevation of a T-junction of a half-brick  wall with dead ends.  
1.8 ct

1.8.1 Identify bricks A. (1) 
1.8.2 Use ANSWER SHEET 1.8.2 and project and draw, from the given  front elevation, the plan course of a T-junction of course BB.  The position of the T-junction is indicated with a cross (X) on the  first course. (4)

1.9 Name ONE type of material that may be used for ceilings. (1) 
1.10 Explain why cavity walls must have weep holes. (1)

[30]

QUESTION 2: ADVANCED CONSTRUCTION AND EQUIPMENT 
Start this question on a NEW page. 
2.1 Choose a description from COLUMN B that matches an item in COLUMN A. Write only the letter (A–M) next to the question number (2.1.1–2.1.10) in the  ANSWER BOOK, for example 2.1.11 N. 

COLUMN A 

COLUMN B

2.1.1 Key brick  
2.1.2 Twisted ribbed bar 
2.1.3 Short-bored piles 
2.1.4 Wall ties 
2.1.5 Plywood 
2.1.6 Multiprop 
2.1.7 Rough arch 
2.1.8 Dry wall 
2.1.9 Focusing knob/screw 
2.1.10 Pre-cast concrete pile

A adjustable support that may be used  individually or combined with frames  to support formwork
B driven into the ground with a drop  hammer
C erecting of scaffolds 
D essential part in the centre of an arch 
E provides colour and coverage 
F suitable for use in solid soil 
G part of a dumpy level 
H hold the inner and outer walls of the  cavity wall together 
I construction process that does not  use bricks 
J used where ground conditions are not  suitable for normal foundations 
K consists of an uneven number of  layers of veneer and may be used for  partitioning 
L reinforcement in concrete 
M must be plastered to finish off 

(10)

2.2 FIGURE 2.2 below shows hand tools that are used on a site and in a workshop.  Write down the name and ONE use of each of the tools next to the question  number (2.2.1–2.2.4) in the ANSWER BOOK.  (8)
2.2 ct
2.3 FIGURE 2.3 below shows an incomplete sectional view of a reinforced beam  and column. 
2.3 ct

2.3.1 Predict TWO negative consequences of not having reinforcement  in concrete. (2) 
2.3.2 Explain why the main bar is placed at the bottom of the beam. (1) 
2.3.3 Explain why the stirrups in a beam are placed closer to each other  near the support. (1)

2.4 The accessories below are used to test fresh concrete: 

  • Mould with a diameter of 100 mm at the top, 200 mm at the bottom and  a height of 300 mm
  • Baseplate 3 mm thick and 600 mm by 600 mm
  • Steel rod 16 mm in diameter and 600 mm long 

2.4.1 Name the test that may be performed with the above accessories. (1)
2.4.2 Explain why it is necessary to conduct this test. (1)
2.4.3 How often must this test be carried out? (1) 

2.5 Explain TWO advantages of cavity walls. (2) 
2.6 FIGURE 2.6 below shows two concrete columns with defects caused by  forces acting on them. 
2.6 ct
Name the type of forces responsible for the defects at A to C. (3)
2.7 FIGURE 2.7 below shows a type of formwork used in construction. 
2.7 ct

2.7.1 Identify the formwork in FIGURE 2.7. (1) 
2.7.2 Recommend ONE material that may be placed on the inside  around part A to give a smoother concrete finish. (1) 
2.7.3 What is used to keep parts B together? (1) 
2.7.4 Describe how you would prevent concrete from sticking to the  inside of formwork. (1) 

2.8 Distinguish between the installation of a rib and block floor and an in situ  concrete floor regarding the duration of the installation. (1) 
2.9 Make a neat, well-proportioned, two-dimensional sketch of a hollow block with  a rib on either side of the block, as used in a rib and block floor construction. Show the reinforcement in the ribs. (5)

[40]

QUESTION 3: CIVIL SERVICES 
Start this question on a NEW page. 
3.1 Make neat freehand drawings to indicate the difference between a P-trap and  an S-trap. (2) 
3.2 Give the diameter of the PVC pipe that you would use for the wastewater at  a sink. (1) 
3.3 FIGURE 3.3 below shows a septic tank. Study the drawing and answer the  questions that follow. 
3.3 ct

3.3.1 Label parts A to F. (6)
3.3.2 Describe what happens to the raw sewerage in C. (1)
3.3.3 Explain the purpose of G. (1)
3.3.4 What is the purpose of F? (1) 
3.3.5 Describe the liquid level in C and D when the septic tank is filled to  capacity. (1) 
3.3.6 Explain why you may NOT direct water coming from a bath or sink  into a septic tank. (1) 

3.4 Describe the main function of a storm water system. (1)
3.5 Explain why storm water should NOT be directed into a sewerage system. (2) 
3.6 Explain the purpose of a pressure-reducing valve as used in cold and hot  water installations. (1)
3.7 Distinguish between the purpose of an elbow and the purpose of a  tee coupler/T-fitting, as used in water pipe installation. (2) 
3.8 The temperature of the water in your geyser is too high due to a faulty part.  Name the faulty part that will cause the water to overheat. (1) 
3.9 What type of geyser would you use when the pressure of the incoming water  from the municipality is low? (1) 
3.10 The inside tray of a solar panel is painted a specific colour. Name the colour  and give a reason for using this specific colour. (2) 
3.11 FIGURE 3.11 on ANSWER SHEET 3.11 shows part of a vertical section  through a building.  
Use ANSWER SHEET 3.11. 

3.11.1 Identify A and B. (2)
3.11.2 Complete the drawing by showing the following on the drawing: 

    • The incoming electricity cable in a kick pipe connected to  a meter box at C
    • Distribution board at D
    • The conduit for the connection from the meter box to the  distribution board at D (4)

[30]

QUESTION 4: QUANTITIES, MATERIALS AND JOINING 
Start this question on a NEW page. 
4.1 FIGURE 4.1 below shows the front view of a hollow-core flush panel door.  Study the drawing and complete the incomplete cutting list. Write down the answer next to the question number (4.1.1 to 4.1.7) in the ANSWER BOOK. 
4.1 ct

MEMBER 

QUANTITY 

UNIT 

LENGTH 

WIDTH 

THICKNESS 

MATERIAL

4.1.1 

mm 

2 032 

50 

38 

SA pine

Top rail 

mm 

693 

4.1.2 

38 

SA pine

Lock block 

mm 

4.1.3 

50 

38 

SA pine

Plywood panel 

mm 

2 032 

813 

4.1.4 

Plywood

Bottom rail 

mm 

4.1.5 

50 

38 

SA pine

Cardboard door  filling 

mm 

4.1.6 

690 

38 

Cardboard

Edging 

mm 

2 032 

44 

4.1.7 

Meranti 

(7)

4.2 Various options are provided as possible answers to the following questions.  Choose the answer and write only the letter (A–D) next to the question  number (4.2.1–4.2.7) in the ANSWER BOOK, for example 4.2.8 C. 

4.2.1 When joining copper pipes using the capillary method, you will ... the two pipes together.  

    1. weld
    2. solder 
    3. glue
    4. tape (1) 

4.2.2 You can join ... pipes using the capillary method. 

    1. copper
    2. copper and PVC 
    3. copper and galvanised 
    4. copper, PVC and galvanised (1) 

4.2.3 When fixing a cornice to a wall, you will use ... 

    1. panel pins.
    2. wire nails. 
    3. steel cut nails.
    4. steel/masonry nail. (1) 

4.2.4 A compression joint may be used to join ... pipes. 

    1. copper
    2. PVC
    3. galvanised
    4. All of the above (1) 

4.2.5 ... is used for joining roof trusses to brickwork. 

    1. Hoop iron
    2. Building line
    3. Cement
    4. None of the above-mentioned (1) 

4.2.6 ... may be used to join polyethylene pipes. 

    1. Wood glue
    2. Insulation tape 
    3. Contact glue
    4. PVC weld solvent (1) 

4.2.7 Type of screw used when the head of the screw must be flush to  the surface of the timber: 

    1. Coach screw
    2. Round head screw 
    3. Countersunk head screw 
    4. Round head countersunk screw (1)

4.3 FIGURE 4.3 below shows the floor plan of a storeroom of which the walls  need to be plastered.  
4.3 ct

SPECIFICATIONS: 

  • Outside measurements of the storeroom: 8 000 mm x 4 000 mm
  • Height of the walls: 2 700 mm
  • Thickness of the walls: 220 mm 
  • Thickness of the plaster: 12 mm 
  • Size of the window: 1 200 mm x 900 mm 
  • Size of the door opening: 2 100 mm x 900 mm 

Use ANSWER SHEET 4.3 and calculate the: 

4.3.1 Total area of the inside of the building that must be plastered.  Ignore the reveals. (13) 
4.3.2 Volume of plaster needed for the internal walls (3)

[30]

QUESTION 5: APPLIED MECHANICS 
Start this question on a NEW page. 
5.1 FIGURE 5.1 below shows a shaped lamina with a square hole. All dimensions  are in millimetres. 
Study the lamina and answer the questions that follow by writing only the  answer with the unit next to the question number (5.1.1–5.1.7) in the  ANSWER BOOK, for example 5.1.8 2 900 mm².  
HINT: Use the formulae on the FORMULA SHEET.
5.1 ct

5.1.1 Calculate the area of part 1. (1)
5.1.2 Calculate the area of part 2 without the hole. (1)
5.1.3 Calculate the area of part 3. (1)
5.1.4 Calculate the total area of the lamina. (1)
5.1.5 Calculate the position of the centroid of part 2 from A–A. (1)
5.1.6 Calculate the position of the centroid of part 1 from B–B. (2)
5.1.7 Calculate the position of the centroid of part 2 from B–B. (1)

5.2 ANSWER SHEET 5.2 shows TWO diagrams of a cantilever frame. Use ANSWER SHEET 5.2 to answer the following questions. 

5.2.1 Name DIAGRAMS A and B. (2) 
5.2.2 On DIAGRAM A, indicate the nature of the forces in each member by  means of arrows. (4) 
5.2.3 Complete the table by indicating the nature and magnitude of the  forces. (Deduce the information from the drawings given.) (6) 

5.3 FIGURE 5.3 below shows the space diagram of a beam with a span of  10 metres with two point loads and a uniformly distributed load. Study the  diagram and answer the questions that follow. 
5.3 ct

5.3.1 Deduce from FIGURE 5.3 the value of the shear forces at A, B, C, E and F and draw the shear force diagram on ANSWER SHEET 5.3.  Indicate the value of the shear forces on the diagram.  
Use scale 1 mm = 1 N. (7) 
5.3.2 Calculate the bending moment at D. (3)

[30]

QUESTION 6: GRAPHICS AND COMMUNICATION 
6.1 FIGURE 6.1 below shows the site plan of a proposed dwelling. Study the  drawing and complete the table on ANSWER SHEET 6.1. 
6.1 ct (15) 
6.2 FIGURE 6.2 below shows a line diagram of the floor plan of an office with  a storeroom. 
6.2 ct
Study FIGURE 6.2 and develop and draw, on ANSWER SHEET 6.2, to  scale 1 : 50, the FLOOR PLAN of the building. Use the specifications below  and on the next page. (Use the assessment criteria on ANSWER SHEET 6.2  as a guideline for your drawing.) 
SPECIFICATIONS: 

  • The measurements indicated on the drawing are the inside measurements of each room. 
  • Windows and doors:

WINDOWS AND DOORS 

WIDTH 

HEIGHT

Window 1 (W1) 

1 500 

1 200

Window 2 (W2) 

900 

600

Door 1 (D1) 

900 

2 100

  • All windows are positioned in the middle of the external wall of each  room.
  • All doors are positioned 300 mm from the wall to the right of the door.
  • The door of the storeroom is positioned in the middle of the wall shared  by the office and the bathroom.
  • All external walls of the house are 220 mm wide. 
  • All internal walls are 110 mm wide.
    The following must also be shown on the floor plan:
  • The drawing symbols for a hand basin, water closet and double-bowl  sink, as indicated by the abbreviations on the line diagram 
  • The total internal dimensions of the office on the western side of the  building 
  • The dimensions of the thicknesses of the walls and sizes of rooms on  the western side of the office 
  •  Labels for the floor coverings for each room 
  • The windows and doors in the spaces, as indicated on the line diagram

THREE marks will be allocated for the application of the scale. 
Start the drawing from corner A, as indicated in the bottom left-hand corner of  ANSWER SHEET 6.2. (25)

[40] 
TOTAL: 200

CENTRE NUMBER: 

                                                           

 

EXAMINATION NUMBER: 

                                                                                                

ANSWER SHEET 1.3  
answer sheet 1.3 ct

ASSESSMENT CRITERIA 

MARK 

CANDIDATE'S  MARK

Roof covering correctly drawn 

1

 

Beam filling correctly drawn 

2

 

Wall plate correctly drawn 

1

 

Any two labels 

2

 

TOTAL 

6

 

 

CENTRE NUMBER: 

                                                              

 

EXAMINATION NUMBER: 

                                                                                                 

ANSWER SHEET 1.8.2 

1.8.2
answer sheet 1.8.2 a
answer sheet 1.8.2 b

ASSESSMENT  

CRITERIA

MARK 

CANDIDATE'S  MARK

Stretcher course 

2

 

Header course 

1

 

Correctness of T-junction 

1

 

TOTAL 

4

 

 

CENTRE NUMBER: 

                                                             

 

EXAMINATION NUMBER: 

                                                                                                  

ANSWER SHEET 3.11 
answer sheet 3.1.1
A: ________________________________ (1)
B: ________________________________ (1) 

ASSESSMENT  

CRITERIA

MARK 

CANDIDATE'S  MARK

Incoming cable 

2

 

Meter box 

1

 

Distribution board 

1

 

TOTAL 

4

 

 

CENTRE NUMBER: 

                                                          

 

EXAMINATION NUMBER: 

                                                                                                 

ANSWER SHEET 4.3 
Complete your answers in the spaces indicated with _____________. 
4.3.1 

D

     

Area to be plastered:

     

Length of ONE short wall:

     

= ______ – 2/________ 

= ______

     

Length of ONE long wall:

     

= _____ – 2/________ 

= _______

     

Total length of one short and one long wall

     

= _____________ + _____________ = _____________ (3)

       

2/ 

_______ 

 

Area of internal walls before deductions:

 

_____ 

_____ m2

 (2)
       

1/ 

_______ 

 

Area of window opening:

 

_______ 

_____ m2

  (2)
       

1/ 

_______ 

 

Area of door opening:

 

_____ 

_____ m2

  (2)
       
     

Total wall area to be plastered

     

= _____________ - _____________ - ______________

     

=_______________ m

(2)

4.3.2   (3)

     

Volume of plaster needed:

1/ 

______

   
 

______ 

________ 

 

 

CENTRE NUMBER: 

                                                           

 

EXAMINATION NUMBER: 

                                                                                                 

ANSWER SHEET 5.2 
answer sheet 5.2 a

 DIAGRAM A __________________________ (1) 
answer sheet 5.2 b

 DIAGRAM B ________________________ (1)
SCALE: 1 mm = 1 N 

MEMBER 

NATURE 

MAGNITUDE

BC

   

CD 

 

---

DA

   

BD 

 

---

(6)
Tolerance of 1 N to either side 

CENTRE NUMBER: 

                                                             

 

EXAMINATION NUMBER:

                                                                                                  

ANSWER SHEET 5.3 
answer sheet 5.3

ASSESSMENT CRITERIA 

MARKS 

CANDIDATE'S  MARK

Drawing correct 

5

 

Indicate all values of shear  forces on drawing

1

 

Correct application of scale 

1

 

TOTAL 

7

 

 

CENTRE NUMBER: 

                                                          

 

EXAMINATION NUMBER: 

                                                                                                    

ANSWER SHEET 6.1

NO. 

QUESTIONS 

ANSWERS 

MARKS

Name the scale used for the site plan. 

 

1

2

State the colour that you would use to  indicate the proposed dwelling on the  site plan. 

 

1

Identify number 1. 

 

1

Identify the line at number 2. 

 

1

Identify number 3. 

 

1

6

Determine the distance from the  boundary line to the proposed dwelling  to the right of the building.

 

1

Identify number 4. 

 

1

Identify number 5. 

 

1

9

Draw the roof line of a hipped roof for  the building.

 

4

10 

Calculate the perimeter of the  proposed dwelling. 

 

2

11

Which elevation will be closest to Long Street? 

 

1

   

TOTAL 

15

 

CENTRE NUMBER: 

                                                          

 

EXAMINATION NUMBER: 

                                                                                                    

ANSWER SHEET 6.2

ASSESSMENT CRITERIA 

MARKS 

LM

External walls 

4

 

Internal walls 

3

 

Windows 

3

 

Doors 

3

 

Wash basin 

1

 

Water closet 

1

 

Double-bowl sink 

1

 

Dimensions 

4

 

Floor coverings 

2

 

Application of scale 

One or two incorrect = 3 Three or four incorrect = 2 More than five incorrect = 1 No measurement correct = 0 

3

 

TOTAL 

25

 

FORMULA SHEET 
IMPORTANT ABBREVIATIONS 

SYMBOL 

DESCRIPTION 

SYMBOL 

DESCRIPTION 

SYMBOL 

DESCRIPTION

Centroid 

Breadth/Width 

Radius

ℓ 

Length 

Side 

Area

FORMULAE 

AREA OF 

FORMULA  

(in words)

FORMULA  

(in symbols)

FORMULA FOR THE  

POSITION OF CENTROIDS

X-axis 

Y-axis

Square 

side × side 

s × s

s/2 

s/

Rectangle 

length × breadth 

ℓ × b

ℓ /2

b/

Right-angled  

triangle 

½ x base × height 

½b × h

b/3 

h/

Equilateral  

triangle/  

Isosceles  

triangle

½ x base × height 

½b × h

b/

h/

Position of centroid = (A1×d) ± (A2 ×d)     
                                       Total area 
OR 

Y = ∑Ay
       ∑A 

OR 

X = ∑Ax
       ∑A 

Last modified on Friday, 13 August 2021 13:37