CIVIL TECHNOLOGY
GRADE 12 
NSC PAST PAPERS AND MEMOS
FEBRUARY/MARCH 2018

MEMORANDUM 

QUESTION 1: CONSTRUCTION, SAFETY AND MATERIAL 
1.1
1.1.1 B ✔ (1) 
1.1.2 E ✔ (1) 
1.1.3 A ✔ (1) 
1.1.4 D ✔ (1) 
1.1.5 F ✔ (1) 
1.1.6 C ✔ (1) 
1.1.7 H ✔ (1) 
1.1.8 I ✔ (1) 
1.1.9 G ✔ (1) 
1.1.10 J ✔ (1) 

1.2
1.2.1 A – To protect your feet against falling objects. ✔ (1) 
1.2.2 B – To protect your feet when working with wet material. ✔ (1) 

1.3 The paint conceals defects ✔ (1) 
1.4

  • Excavations must be fenced off. ✔
  • Red warning lights should be placed at intervals to warn the public. ✔
  • All excavations must take place under supervision. 
  • The contractor must test the stability of the terrain before  commencement of excavations.
  • Shoring should be cross braced.
  • Bracing should be strong enough to support the shoring.
  • No tools or materials other than those in use are allowed inside the  trench when excavations are in progress.
  • Access to the excavation should be safe e.g. ladders can be used.
  • A responsible person must inspect and investigate underground  electricity and water supply.
  • The sides should be braced and protected if deeper than 1,5 meters.
    ANY TWO OF THE ABOVE OR ANY OTHER ACCEPTABLE ANSWER (2) 

1.5

  • Baseplate ✔
  • Mould/Cube ✔
  • Tamping rod ✔
  • Plaster trowel/straight edge/shovel
    ANY THREE OF THE ABOVE (3)

1.6

  • Water makes the fresh concrete workable. ✔ 
  • Water acts as a lubricant.
  • Water is also needed for the hydration process.
    ANY ONE OF THE ABOVE (1) 

1.7
1.7.1To prevent moisture from getting into the building. ✔ (1) 
1.7.1 To prevent moisture from moving up in the walls. ✔ (1) 
1.8

  • Preservatives with a base of water-soluble salts. ✔
  • Varnish
    ANY ONE OF THE ABOVE (1)

1.9 Roof tiles/Clay tiles/Concrete tiles ✔ (1)
1.10 Ridge capping ✔ (1)
1.11 Gang nails/plate connectors ✔ (1) 
1.12 WITH TICKS(5) 

ASSESSMENT CRITERIA 

MARK 

CANDIDATES  MARK

One brick wall 

2

 

Half brick wall 

(T-junction) 

1

 

Three-quarter bricks 

2

 

TOTAL 

5

 

[30]
QUESTION 2: ADVANCED CONSTRUCTION AND EQUIPMENT 
ANSWER THIS QUESTION ON A NEW PAGE.
2.1
2.1.1 C ✔ (1)
2.1.2 D ✔ (1)
2.1.3 A ✔ (1)
2.1.4 B ✔ (1)
2.1.5 A ✔ (1) 
2.2
2.2.1 Portable electric generator ✔ – It is used to generate electricity ✔ (2) 
2.2.2 Portable electric circular saw ✔ – It is used for cross cutting and  ripping of timber. ✔ (2) 
2.3 Chalk line ✔ (1) 
2.4

  • Flat steel square ✔
  • Tape measure
    ANY ONE OF THE ABOVE (1) 

2.5

  • Rough arch will be built with common bricks ✔
  • Gauge arch will be built with face bricks ✔ (2)

2.6
2.6.1 Driven in-situ pile ✔ (1) 
2.6.2

  • Low bearing capacity of soil ✔
  • Subsoil – subjected to movement ✔
  • Subsoil – subjected to high moisture content.
  • Recently placed filling materials that is not sufficiently  compacted
  • Unstable soil structure
  • High water table
    ANY TWO OF THE ABOVE (2)

2.6.3 Steel reinforcement ✔ (1)
2.7
2.7.1 Twisted square bar ✔ (1)
2.7.2 Round bar (mild steel) ✔ (1) 
2.8 

  1. – Landing ✔
  2. – Rise ✔ 
  3. – Tread ✔ (3) 

2.9

  • Blow holes ✔
  • Uneven colour/discoloration ✔
  • Honey comb effect/Leaking of grout 
    ANY TWO OF THE ABOVE (2)

2.10
2.10.1 Cavity wall ✔ (1) 
2.10.2

  • A – Wall tie ✔
  • Keeps the two skins of the wall securely together. ✔
  • It strengthens the wall
    ANY TWO OF THE ABOVE (2) 

2.10.3

  • B – Weak concrete mixture ✔ 
  • Concrete mixture
    ANY ONE OF THE ABOVE (1) 

2.10.4

  • To strengthen the wall below the DPC (damp proof course) ✔
  • To close the cavity below the damp proof course
    ANY ONE OF THE ABOVE (1)

2.10.5 C – Damp-proof membrane ✔ (1)
2.10.6 50 mm ✔ (Unit must be part of the answer) (1)
2.11
2.11.1 

  1. – Cladding (or any cladding material) ✔ 
    • Timber floor board ✔
    • Base plate
    • Base board
      ANY ONE OF THE ABOVE FOR B (2) 

2.11.2

  • Steel ✔
  • Metal
  • Aluminium
    ANY ONE OF THE ABOVE (1) 

2.11.3

  • There is no wet material ✔
  • There is no heavy material to carry ✔
  • Dry walls are light in weight.
  • Dry walls are easier to install 
  • Dry walls are easy to remove if required
    ANY TWO OF THE ABOVE (2)

2.12
2.12.1 Rib and Block floor ✔ (1) 
2.12.2 

  1. – Rib ✔ 
  2. – Hollow block/Block ✔ 
  3. – Reinforcing steel/Steel rod/Reinforcement ✔ (3) [40]

QUESTION 3: CIVIL SERVICES 
3.1
3.1.1 P-trap ✔ (1) 
3.1.2 Washbasin/Urinal/Shower/Sink ✔ (1) ANY ONE 
3.2
3.2.1

  1. -Is the inlet pipe for cold water ✔
  2. -Is the outlet pipe for warm water ✔ (2) 

3.2.2 To shut down water supply during maintenance. ✔ 
ANY OTHER ACCEPTABLE ANSWER (1) 
3.2.3

  • To prevent water from leaking through the ceiling ✔
  • It is compulsory to install a drip tray 
    ANY ONE OF THE ABOVE (1) 

3.3
3.3.1 Storm water is hail, snow, rain that falls to the earth in large  quantities. ✔ 
ANY OTHER ACCEPTABLE ANSWER (1) 
3.3.2 Storm water is guided into the channels where after the water is  guided to storm water pipes and catchment areas. ✔ 
ANY OTHER ACCEPTABLE ANSWER (1) 
3.4 Water in shallow wells is:  

  • Easily dug out ✔
  • Cheap 
  • Relatively reliable 
    ANY ONE OF THE ABOVE (1)

3.5 Wind pump ✔ (1)
3.6 FRIDGE(8) 

ASSESSMENT CRITERIA

MARK 

CANDIDATE'S  MARK

2 way light switch 

2

 

Socket outlet 

2

 

Light 

2

 

Electrical wire 

2

 

TOTAL 

 

3.7 ANSWER SHEET 3.7 
TANK(12)

ASSESSMENT  CRITERIA

MARK 

CANDIDATE'S  MARK

Rodding eye 

1

 

Gully 

1

 

Vent pipe 

1

 

Main sewerage pipes 

2

 

Inspection eyes 

4

 

Manhole 

1

 

Any TWO  

abbreviations for the  sanitary fixtures

2

 

TOTAL 

12

 

 [30] 

QUESTION 4: QUANTITIES, MATERIALS AND JOINING 
4.1
4.1.1

  • Gang nail ✔ (1)
    USE:
  • Gang nails are used to join the members of roof trusses. ✔
  • Extend the length of a timber board/beam. 
    ANY ONE OF THE ABOVE USES (1) 

4.1.2

  • Bolt and nut ✔ (1)
    USE:
  • Bolts and nuts are used to join the members of roof trusses. ✔ 
  • Join material to brackets 
  • To fix truss hangers to rafters
    ANY ONE OF THE ABOVE USES (1) 

4.1.3

  • Dry wall screw ✔ (1)
    USE:
  • Drywall screws are used to fix dry wall materials. ✔
  • Joining ceilings and battens to other members 
  • Joining timber to each other (1)
    ANY ONE OF THE ABOVE USES 

4.2

  • Rawl bolt/Expansion anchor ✔ 
  • Sleeve anchor 
  • Dina bolt
    ANY ONE OF THE ABOVE (1) 

4.3

  • Compression joint ✔
  • Capillary joint
    ANY ONE OF THE ABOVE (1) 

4.4

  • Screws have greater holding power than nails ✔
  • They can be fixed where vibration has to be avoided ✔
  • Screws can easily be removed 
  • The appearance of screws is better in finishing than nails
    ANY TWO OF THE ABOVE (2)

4.5
4.5.1 38 or 38 mm ✔ (1)
4.5.2 2 349 or 2 349 mm ✔ (1)
4.5.3 5 √ (1)
4.5.4 2 575 or 2 575 mm ✔ (1)
4.5.5 5 150 or 5 150 mm ✔ (1)
4.5.6 4 500 or 4 500 mm ✔ (1)
4.5.7 10 300 or 10 300 mm ✔ (1)
4.6 

D

     

Inside measurement of:

     

Long walls = 6 500 – 2/220 ✔

     

= 6 060 mm ✔

     

Short walls = 3 800 – 2/220 ✔

     

= 3 360 mm ✔

     

(4)

1/ 

6,06 

 

Inside floor area of the room is 

 

3,36 ✔ 

20,36 m2

(2)

       
     

Area of one ceiling board:

1/

3,9 

 

One board is 3 900 mm x 900 mm

 

0,9 ✔ 

3,51 m2 ✔

(3)

       
     

Length of skirting:

     

= 2(6 060 ✔+ 3 360 ✔) – 900 mm ✔

     

= 17,94 m ✔

     

OR 12 120 + 6 720 - 900

     

=17,94 m

     

OR 6 060 + 6 060 + 3 360 + 3 360 - 900

     

=17,94 m

     

(4)

     

(13)

[30]
QUESTION 5: APPLIED MECHANICS 
5.1
5.1.1

  • (A1 x d) + (A2 x d) 
     Total area
    = (3 200 x 20) + (900 x 60) 
                       4 100 ✔
    = 64 000 mm3 + 54 000 mm
                      4 100
    = 118 000 mm3 ✔ 
         4 100 mm2 
    = 28,78 ✔ mm ✔ 

OR 

Part 

Area (A) 

AY

3 200 mm² ✔ 

20 mm ✔

3 200 x 20 = 64 000  mm3

900 ✔ mm² 

60 mm ✔ 

900 mm x 60 mm =  54 000 mm3

∑ 

4 100 mm² ✔ 

 

118 000 mm

  • Y  = ∑ Ay 
           ∑ A
    = 118 000 mm3 ✔ 
        4 100 mm2 
    = 28,78 ✔ mm ✔ (10)

5.2.1 

SAVE 5.2 ANSWER(8) 

MEMBER 

NATURE 

MAGNITUDE

FG 

Tie ✔ 

23 N ✔

BF 

Strut ✔ 

50 N ✔

Tolerance of 1 N to either side   (4)
NOT TO SCALE DUE TO ELECTRONIC TRANSFER USE A MASK TO MARK THIS QUESTION 
5.3
5.3.1 40 Nm ✔ (1)
5.3.2 7 m ✔ (1)
5.3.3 3 m ✔ (1)
5.3.4 
5.3 ANSA(5) 
SCALE 1 mm = 2 Nm 
NOT TO SCALE DUE TO ELECTRONIC TRANSFER 
USE A MASK TO MARK THIS QUESTION 

  • If the bending moment diagram is not to scale, deduct 1 mark.
  • Marks are allocated for each line between A to F.
  • If the lines between B and D are straight lines no marks will be awarded for  these lines. [30] 

ANSWER SHEET 6.1

NO. 

QUESTIONS 

ANSWERS 

MARKS

Name the scale used for the West  elevation.

1:100 ✔

1

Identify number 1. 

Barge board ✔ 

1

Identify number 2. 

Window/window pane/glass  casement ✔

1

Identify number 3. 

Door/door opening ✔ 

1

Identify number 4.

FFL/Finished floor level ✔ 

1

Identify number 5. 

Step ✔ 

1

Identify number 6. 

NGL/Natural ground level ✔ 

1

Identify number 7. 

Window sill ✔ 

1

Name the material that can be  used for the soffit board at a closed  eave?

Fibre cement ✔

1

10 

Recommend a suitable exterior  finish for the wall. 

Paint/plaster/face brick/  cladding ✔

1

11 

Deduce on which elevations will the  gutters be placed in this house? 

North elevation ✔ and South  elevation✔

2

12 

Draw the roof lines for the roof of  the building shown in FIGURE 6.1 in the column alongside.

DOTTED

3

   

TOTAL 

15

QUESTION 6: GRAPHICS AND COMMUNICATION
ANSWER SHEET 6.2 
KINGS POST

ASSESSMENT  CRITERIA 

MARKS 

LM

Correctness of  

drawing 

3

 

External wall 

1

 

Symbol for wall 

1

 

Plaster 

2

 

Wall plate 

1

 

Tie beam 

1

 

Rafters 

2

 

King post 

1

 

Brandering 

1

 

Ceiling board 

1

 

Cornice 

1

 

Fascia board 

1

 

Print title and scale 

2

 

Any FOUR labels 

4

 

Application of scale:

  • One or two incorrect  = 3
  • Three or four incorrect  = 2
  • More than five  incorrect = 1
  • No measurement  correct = 0 

3

 

TOTAL 

25

 

[40]
200 

Last modified on Thursday, 05 August 2021 12:41