CIVIL TECHNOLOGY(CIVIL SERVICES)
GRADE 12
NATIONAL SENIOR CERTIFICATE
MEMORANDUM
NOVEMBER 2019

QUESTION 1: OHSA, SAFETY, MATERIALS, TOOLS, EQUIPMENT AND JOINING (GENERIC)
1.1
1.1.1 B ✓(1)
1.1.2 I ✓ (1)
1.1.3 A ✓ (1)
1.1.4 G/H ✓ (1)
1.1.5 C ✓ (1)
1.1.6 F ✓ (1)
1.1.7 J ✓ (1)
1.1.8 E ✓ (1)
1.2 Electroplating:

  • protects metals against corrosion. ✓
  • improves the engineering- and mechanical properties of metal. ✓
  • may be used to increase the thickness of undersized parts.
  • is decorative.
  • will extend the life span.
    ANY TWO OF THE ABOVE (2)

1.3 Curing ✓ (1)
1.4 The moisture:

  • delays/prevents the rapid drying of fresh concrete.
  • prevents concrete from cracking. ✓
  • ensures that fresh concrete hardens properly.
  • allows adhesive bonding.
  • increases strength of fresh concrete.
    ANY ONE OF THE ABOVE (1)

1.5

  • When material is transported in bulk, it must be secured firmly. ✓
  • When material is transported to higher levels, make sure that workers maintain a safe distance from the material being moved overhead. ✓
  • When heavy material is transported with a lift/hoist/machine, a qualified person must take charge of operations.
  • Wear appropriate personal protective equipment(PPE).
  • Material must be transported in a safe way.
  • Transport should not be overloaded with material.
    ANY TWO OF THE ABOVE (2)

1.6 Scaffold planks should:

  • be made of a solid wood at least 228 mm wide and 38 mm thick. ✓
  • be able to support the load.
  • be free from defects.
  • not be painted as it will hide defects/be slippery.
  • be supported at distances not exceeding 1,25 m.
  • not project less than 70 mm and not more than 230 mm beyond the ends of the last prop.
  • be firmly secured to prevent its displacement.
  • be placed in such a way to prevent materials and tools from falling through.
    ANY ONE OF THE ABOVE (1)

1.7
1.7.1 Dumpy level ✓ (1)
1.7.2 If the dumpy level is not set up level:

  • it will give inaccurate readings. ✓
  • wrong levels will be transferred.
  • true levels will not be transferred.
    ANY ONE OF THE ABOVE (1)

1.8
1.8.1 A – Plastic plug/Plug/Rawl plug/Fisher plug/Fibre plug ✓ (1)
1.8.2 A screw ✓ (1)
1.8.3 Plastic plugs are used to secure:

  • cupboards against a wall. ✓
  • mirrors against a wall.
  • portraits and similar objects against a wall.
  • objects, limited to certain weight, against walls.
    ANY ONE OF THE ABOVE (1)

[20]

QUESTION 2: GRAPHICS AS MEANS OF COMMUNICATION (GENERICS)
ANSWER SHEET 2

ANSWER SHEET 2

NO.  QUESTION ANSWER MARKS
1 Identify the elevation in FIGURE A.  West Elevation ✓  1
Identify the type of roof that is used on the building in FIGURE A.  Hipped roof ✓  1
Identify number 1.  Ridge Capping/Ridge plate/Ridge tile/Hip cap ✓  1
Identify number 4  Balcony/Floor slab of balcony/Cantilever/Concrete slab ✓  1
Identify number 5 External door/Entrance door/Door/Outside door ✓  1
6 Identify number 7 Gutter ✓  1
Identify number 8 Rainwater down pipe/RWDP/Down pipe ✓  1
8 Identify number 12 Wash trough/Wash tub ✓ 1
9 Identify number 13 Built-in cupboard/BIC ✓ 1
10 Identify number 15 Landing ✓ 1
11 Identify the company that printed the building plan. Dlamini printers ✓ 1
12 Name a suitable material that can be used for the manufacturing of number 2. Fibre cement/Galvanised sheeting/ Timber/Plastic/PVC/Polyvinylchloride✓ 1
13 Name the drawing symbol in the column for the notes in FIGURE 2 that must be installed in the kitchen. Electricity meter/Electrical meter/Watt meter/Prepaid meter✓ 1
14 Name the drawing symbol in the column for the notes in FIGURE 2 that indicates the type of bricks for the building Face brick ✓ 1
15 Name a material that should NOT be used to manufacture the frame of number 9 for coastal areas. Steel/Mild steel/Iron/Ferrous metals ✓ 1
16 Name a material that can be used to manufacture the sanitary fitting indicated by number 11. Stainless steel/Plastic/Ceramic/
Granite/Acrylic/Fibre
Glass/Concrete✓
1
17 Who checked the building plan? P Carter ✓ 1
18 How many types of windows are used in FIGURE B? 2 ✓ 1
19 What does the abbreviation NGL at number 6 stand for? Natural ground level ✓ 1
20 Give the reference code for this plan. QP 2-2019✓ 1
21 Which room will electrical symbol 16 serve? Lounge ✓  
22 Describe the purpose of number 3. Prevent people from falling off/through. ✓✓ 2
23 Explain what the curved lines between the electrical installations in FIGURE B indicate. Electrical wiring/Wiring/Electrical cable/Wiring from light switch to light/Shows which switch operates which electrical fitting. ✓✓ 2
24 Explain why the light switch is mounted on the outside of the bathroom. To prevent steam/moisture entering the switch/To prevent electrical shock due to moisture/For safety purposes ✓ 1
25 Identify in FIGURE 2 which elevation does NOT have windows. North elevation ✓ 1
26 Identify the thickness of the internal wall in FIGURE 2. North elevation ✓ 1
27 Differentiate between symbols 13 and 15 in terms of their purpose. 110mm 2
28 Justify why FIGURE B is a ground floor plan 13 – Built-in cupboard: to store items. ✓
15 – Landing: to rest/safety feature/change of direction of stairs ✓
1
29 Predict what will happen if number 10 is NOT installed.

Ground floorplan:

  • does not indicate the roofline ✓
  • does not indicate the balcony
  • indicate an entrance door to the house
  • indicate a step at the entrance door
  • the position of the windows and door correlate with the positions of the window and door on the west elevation
1
30 Redraw the staircase in FIGURE B in the adjacent column and indicate the direction of the flight with arrows. 19 2
31 Calculate the total length of the wall on the eastern side of the building. Show ALL calculations.

220 ✓ + 2 600 ✓ + 110 ✓ + 3 400 ✓+ 220 ✓
= 6 550 mm or 6,55 m✓
IF INCORRECT METHOD IS USED TO CALCULATE THE ANSWER
USE THE FOLLOWING SLIDING SCALE:

  • 4 MARKS WILL BE AWARDED IF ALL FIVE VALUES ARE CORRECT
  • 3 MARKS FOR FOUR VALUES CORRECT
  • 2 MARKS FOR THREE VALUES CORRECT
  • 1 MARK FOR 2 VALUES CORRECT
6
  TOTAL:   40

 

QUESTION 3: CONSTRUCTION ASSOCIATED WITH CIVIL SERVICES, OHSA, AND QUANTITIES (SPECIFIC)
3.1.1 Step irons/Ladder/Concrete/Cast iron lid (ANY ONE)✓(1)
3.1.2 Step irons/Ladder/Concrete/Cast iron lid (ANY ONE) ✓ (1)
3.2
3.2.1 Wedge ✓ (1)
3.2.2 300 mm ✓ (1)
3.3
3.3.1 4✓ (1)
3.3.2 3 ✓ (1)
3.3.3 L x b x h OR Area of base x height OR Side x side x side OR S3
= 2,7 ✓x 2,7 ✓ x 2,7 ✓
= 19,68 m³ ✓ (4)
= 19,68 m³ x 1 000 ℓ ✓
= 19 680 ℓ OR 19 683 ℓ ✓ (2)
3.4
3.4.1 D- Clip ✓ (1)
3.4.2 Rope grab ✓ (1)
3.4.3 Breathing apparatus ✓ (1)
3.4.4 Transparent pipe level ✓ (1)
3.4.5 Manhole ✓ (1)
3.5

  1. – Spirit level ✓
  2. – Long straight edge/Straight edge✓
  3. – Steel peg/Peg ✓ (3)

3.6 
20

QUESTION 4: HOT- AND COLD-WATER SUPPLY, TOOLS, EQUIPMENT AND MATERIALS (SPECIFIC)
4.1
4.1.1 Solar geyser system/Solar panel with geyser ✓ (1)
4.1.2 Water will get cold. ✓ (1)
4.1.3 To ensure maximum operation/efficiency. ✓
So that dirt cannot accumulate on the glass panel.
ANY ONE OF THE ABOVE (1)
4.2 An airlock is a pocket of air ✓ that is trapped inside ✓ a pipe and it prevents constant water flow. ✓ (3)
4.3 Causes of water hammer are:

  • Sudden drop in secondary supply pipes ✓
  • Loose jumpers in taps ✓
  • Pipes in walls are not properly caulked
  • Pipes are not properly secured in roof spaces above the ceiling
  • Draw-off pipe is bigger than the supply pipe
  • Bad/Poor installation
    ANY TWO OF THE ABOVE (2)

4.4
4.4.1 Balancing device (hot water control) ✓ (1)
4.4.2 Shower (movable)/Movable shower✓ (1)
4.5
21
4.6
4.6.1 S-Trap✓ (1)
4.6.2 40/50 mm ✓ (1)
4.7
4.7.1

  1. – T Junction (Plain) ✓
  2. – 90º bend with inspection eye✓ (2)

Related Items

4.7.2

  1. – Where three soil pipes with the same diameter meets/Where the branch pipe connects to the main sewerage pipe.✓
  2. – Above ground where soil pipes have to change direction at a 90º angle/Outside the external wall where the water closet is . installed.✓ (2)

4.8
4.8.1 Pipe-thread cutting machine ✓ (1)
4.8.2 Water pressure testing pump ✓ (1)
4.8.3 Drain-cleaning machine/Jetting machine ✓ (1)
4.9 Functions of the centrifugal pump:

  • To pump water out of excavations or trenches. ✓
  • To move liquids through pipes or pipelines.✓
  • To move slurries or liquid containing suspended matter.
  • To convert rotational motion/kinetic energy to hydrodynamic energy.
  • To increase the pressure of water in pipes.
    ANY TWO OF THE ABOVE (2)

4.10 It is not recommended that copper pipes are joined to galvanised pipes because:

  • Negative effects on the pipeline can be caused due to the chemical reactions between the metals and acidic water✓
  • Pit marks are caused by the chemical reaction between the two metals.✓
  • An electrochemical reaction can take place between two dissimilar metals causing corrosion/dezincification.
    ANY TWO OF THE ABOVE (2)

4.11
4.11.1 Pillar tap✓ (1)
4.11.2 A pillar tap can be used at:

  • Sinks/Kitchen ✓
  • Baths/Bathroom/En-suite✓
  • Basins/Bathroom/En-suite
    ANY TWO OF THE ABOVE (2)

4.12
4.12.1 Water meter ✓ (1)
4.12.2 Full way valve/Stop cock ✓
To shut off the water supply✓ (2)
4.12.3 Bibcock/Bib tap/Garden tap ✓ (1)
4.12.4 No reaction will take place/No ✓(1)
4.12.5 Dezincification ✓(1)
4.13 Water saving devices:

  • Sensor taps ✓
  • Demand pillar taps ✓
  • Metered taps
    ANY TWO OF THE ABOVE (2)

4.14 Pressure control valve reduces/control the incoming water pressure to a building. ✓(1)
Temperature and pressure safety valve will reduce/relieve pressure in a hot water system in case of excessive pressure building up in the geyser. ✓(1)
[40]

QUESTION 5: GRAPHICS AS MEANS OF COMMUNICATION, ROOF WORK AND STORM WATER (SPECIFIC)
5.1
5.1.1 
22
5.1.2 Fascia board/Rafter ✓ (1)
5.2
5.2.1 Surface channel ✓ (1)
5.2.2 Rainwater shoe/Concrete shoe✓ (1)
5.2.3 Road kerb/Kerb ✓ (1)
5.2.4 Flashing ✓ (1)
5.3 Municipality/Local Government/Local Authorities. ✓(1)
23
[30]

QUESTION 6: SEWERAGE, SANITARY FITTINGS AND JOINING (SPECIFIC)
6.1
6.1.1 D ✓ (1)
6.1.2 A✓ (1)
6.1.3 D ✓ (1)
6.1.4 B ✓ (1)
6.1.5 C ✓ (1)
6.2 
24
6.3
25
(4)
6.4
6.4.1 135°✓ (1)
6.4.2 The purpose of the inspection eye is to gain access to the sewer pipe to:

  • inspect it.✓
  • clear blockages/allow for cleaning.
    ANY ONE OF THE ABOVE (1)

6.5 Fittings in a drainage system should:

  • be made of material that is suitable for the piping. ✓
  • remain watertight under normal working conditions. ✓
  • be able to withstand internal water pressure of 50 kPa and external pressure of 30 kPa without leaking.
    ANY TWO OF THE ABOVE (2)

6.6

  • Ventilation pipes/Vent pipe ✓
  • Vent valves ✓ (2)

6.7 Septic tanks:

  • Must be cleaned when the sludge level rises above the outlet and starts flowing out. ✓
  • Soil water is discharged into a French drain. ✓(2)

Vacuum tanks:

  • Must be emptied when it reaches its maximum capacity. ✓
  • Must be cleaned more regularly than a septic tank.
  • Sewage is stored until it is pumped out by the local municipality. ✓
    ANY TWO OF THE ABOVE (2)

6.8
26
6.9
27
ABREVIATIONS ALSO ACCEPTED IN THE PLACE OF THE SYMBOL
A MAXIMUM OF 2 MARKS WILL BE AWARDED IF THE WRONG LINE TYPES ARE USED FOR THE BRANCH PIPES.

ASSESSMENT CRITERIA MARK
BRANCH PIPES  3
VENT PIPE 1
GULLEY’S 2
JUNCTION OF TWO MAIN SEWER PIPES  1
RODDING EYES  2
INSPECTION EYES  3
GRADIENT 1
TOTAL: 13

[40]
TOTAL: 200

Last modified on Tuesday, 07 December 2021 09:33